The entire scanning process took approximately one hour to complete, collecting more than 250 million data points. Source: FARO
A municipal ice rink recently contracted an engineering firm to install new cooling equipment in the mechanical room. The challenge for the engineers was to limit the downtime of the facility while replacing the old cooling unit with new piping, elements and fittings. A carefully drawn out design would have to be planned in order to successfully complete the install.
As-Built The municipality incentivized the installation project by offering the engineering firm a bonus for every day they finished ahead of schedule or a penalty for every day the rink was out of commission past the projected timeline. Obviously, the firm’s objective was to limit the rink’s downtime and complete the update installation as quickly as possible.
To install a new refrigeration unit, the entire mechanical room needed to be modeled, so the mechanical engineer could identify all the existing pipes and how much space was available for the new unit. He would also need to be able to determine what could be updated and replaced before the old unit was disconnected, thus getting a head-start on installing the new parts in the correct locations. Pipes could be pre-installed and simply hooked up when the new unit was brought in. Time meant money to the contract engineering firm, and the quicker and more accurately they could plan the install, the more they stood to gain. Through a previous customer referral, GKS Global Services was chosen as the 3-D scanning provider by the engineering company. GKS was brought in to perform a scan of the entire mechanical room to create a precise 3-D model to facilitate the equipment install.
The mechanical room to be refitted was approximately 30 by 50 feet and full of machines and equipment that operated the ice arena. Everything needed to be modeled to avoid creating interferences between the room’s contents when the new refrigeration unit and the associated piping were installed. The GKS engineer used the FARO Laser Scanner Photon to perform the scan. Since the room was crowded with equipment, six setups were required to capture all the features present with an unobstructed field of view.
The entire scanning process took approximately one hour to complete, collecting more than 250 million data points. The alternate way of acquiring this type of detailed dimensional data would have been to measure everything manually with tape measures and rulers, and to write down each dimension on a two-dimensional hard-copy drawing. This method would have taken at least three weeks to complete, and would have cost at least double the amount spent on laser scanning. The results would not have been as accurate or complete, and prone to human error in measuring and recording the numbers. Also, the z-axis (vertical) measurements would have had to have been recorded on the two-dimensional drawing.
Using laser scanning to map the entire room in 3-D saved the engineering firm at least 65% in time and monetary outlay, from three weeks down to 1 week for scanning and modeling, and from $10,000 to $12,000 down to $5,000 in cost, which includes wages, overtime and consulting.
The scan data of the room and the equipment was collected in an hour and provided accuracies of ±.08 inches; modeling took place in AutoCAD in about three days with an accuracy of ±.5 of an inch. The precise model of the room and its contents allowed the consulting engineers to plan the tear-out in stages, with temporary lines facilitating the switchover. They accomplished all the updates on the plumbing and electric systems before having to go “offline” while replacing the cooling unit.
Because the model was so accurate, the retrofits went in without a hitch. The engineering firm was able to use the scan data layers to separate their work into phases. This made it easy to see the existing configuration, determine what would remain after the installation, what would be removed and where the new equipment would fit. The new geoexchange system was complicated and high-tech, so having the thorough accurate map of the space was a tremendous advantage. Downtime at the rink was minimal, just eight hours while the new system was installed and the pipes were hooked up. Once again the speed of the refurbishing process made possible with laser scanning by GKS saved the municipality from losing revenues in admission and rental charges, and earned the engineering firm payback from the incentive program by finishing ahead of schedule.
As buildings and their physical plants age, fast and accurate 3-D laser scanning is an excellent method to perform updates with minimal disruption of the structures’ functions. Saving both time and money by shortening the renovation process, plus providing more exact results make long-range laser scanning a technique to adopt for many large-scale remodeling, updating, and refurbishing projects.